Newsletter: Activities in WINRIP Project during third Quarter of 2017 (July – September)

Print Friendly

The following is newsletter which contains a summary of the activities in the WINRIP project during July to September 2017. This activity consists of the bid submission and bid opening, contract signing, TPM selection, site visit, training, and others meeting.

Rapat koordinasi dengan para pihak terkait proyek melanjutkan rapat sebelumnya tentang pembahasan membahas  Dokumen Evaluasi Lingkungan Hidup (DELH).Dilanjutkan dengan Cek base camp management pada paket 05 dan 15 untuk memastikan bahwa kontraktor telah menerapkan prinsip base-camp dengan benar dan baik agar tidak terjadi pencemaran lingkungan di Base-camp.​

NO

DATE

ACTIVITY

REMARKS

DOCUMENTATION

1 10 – 13 Juli 2017 Kunjungan Lapangan ke Paket 07, 12, 14, 20 dan 21 dan review meeting paket 17, 16, 08, dan 15.Oleh :

  • Team Leader
  • Co Team Leader
  • Highway Engineer
  • Secretary
Kunjungan Lapangan difokuskan untuk rapat review meeting di base camp Paket 07, 12, 14, 20 dan 21, serta rapat dengan perwakilan dari paket 17, 16, 08, dan 15 di kantor DSC untuk membahas progress dari masing-masing paket. NL03_2017_01
NL03_2017_02
2 10 – 13 Juli 2017 Monitoring implementasi AMDAL dan Training Base Camp Management Paket 08, 20, dan 21 di Provinsi Sumatera BaratOleh :
Environmental Specialist
Monitoring dilakukan dengan tujuan memastikan kontraktor melaksanakan Analisa Dampak Lingkungan (AMDAL) pada tahap konstruksi di masing-masing paket tersebut. Mengadakan Training Base Camp Management di masing-masing paket sehingga pengelolaan base camp sesuai dengan ketentuan. NL03_2017_03
NL03_2017_04
NL03_2017_05
3 17 Juli 2017 Rapat Koordinasi Paket WINRIP Rapat dilaksanakan di Gedung Sapta Taruna Lantai 5, dipimpin oleh Ketua Harian PMU dan dihadiri oleh :

  • Perwakilan World Bank
  • Para Satker
  • Para PPK
  • Tim DSC dan para SSE
  • Tim CTC

Membahas progress masing-masing paket, tantangan, dan rencana percepatan WINRIP.

NL03_2017_06
4 18 Juli 2017 Rapat Usulan Perpanjangan waktu pelaksanaan Paket 07 Indrapura – Tapan. Rapat dilaksanakan di Gedung Sapta Taruna Lantai 7, dipimpin oleh Ketua Pelaksana Harian PIU dan dihadiri oleh :

  • Ketua Harian PMU
  • Satker PJN II Sumatera Barat
  • BPJN III Padang
  • PPK Paket 07
  • Tim CTC
  • Tim DSC dan SSE Paket 07
  • Kontraktor Paket 07

Rapat usulan perpanjangan waktu  dan penyelesaian permasalahan yang ada sehingga pekerjaan dapat diselesaikan sebelum Loan Closing Date.

NL03_2017_07
NL03_2017_08
5 24 – 26 Juli 2017 Environmental Monitoring pada  Base Camp Management,  Paket 05 dan 15 di  Provinsi Sumatera Utara oleh :

  • Environmental Specialist
Monitoring dilakukan dengan tujuan pengecekan manajemen base camp tentang kesesuaiannya dengan ketentuan dan pengecekan penyimpanan aspal, oli dan lain sebagainya agar tidak terjadi pencemaran lingkungan pada masing-masing base camp 05 dan 15. NL03_2017_09
NL03_2017_10
6 25 – 28 Juli 2017 Monitoring Road Safety Audit / Audit Keselamatan Jalan, pada Paket 08, 20 dan 21 di Provinsi Sumatera Barat oleh :

  • Road Safety Engineer
  • Road Safety
Kunjungan dilakukan pada paket-paket  tersebut pada masa konstruksi agar rambu dan fitur keselamatan jalan terpasang sesuai dengan  ketentuan. NL03_2017_11
NL03_2017_12
7 26 -28 Juli 2017 Monitoring pelaksanaan Paket 16 (Seblat – Ipuh)Oleh : Tim TPM dari Universitas Bengkulu, didampingi oleh :Community Develop Officer CTC. Sebagai kewajiban TPM untuk melakukan monitoring pelaksanaan pekerjaan di lapangan terutama permasalahan yang berhubungan dengan msyarakat dan lingkungan sekitar proyek, ketaatan terhadap spesifikasi, dan manajemen hubungan antara stakeholder terkait. NL03_2017_13
NL03_2017_14
8 01 – 04 Agustus 2017 LARAP Monitoring pada Paket 07, 12, dan 14 di provinsi Sumatera Baratoleh :

  • Assisten Social Impact Specialist
Tujuan kunjungan adalah untuk berdiskusi dengan PPK Paket 07, 12, dan 14 mengenai kondisi terakhir mengenai relokasi Warga Terkena Dampak (WTP), dan solusi terakhir untuk pembebasan lahan. NL03_2017_15
NL03_2017_16
9 8 – 11 Agustus 2017 Site visit dan monitoring ke Paket 20,21,14,07 dan 12 di Provinsi Sumatera Barat. Dan ke Paket 04,06,11,13,16 dan 19 provinsi BengkuluOleh:-  Tim PMU,-  Tim PIU dan- Tim CTC yang terdiri dari:Team Leader, CO team Leader, dan Quality Assurance Specialist Monitoring ke beberapa Paket di Provinsi Sumatera Barat dan Meeting di base camp Paket 20, 21, 14, 07, dan 12 untuk membahas kemajuan dan kendala yang ada  dilapangan.Site Inspection ke Paket yang sudah PHO di Provinsi Bengkulu, yaiu: 04, 06, 11, dan 19  dan diakhiri dengan  review meeting di base camp Paket 16 dan paket 13 yang sedang dalam proses konstruksi. NL03_2017_17
NL03_2017_18
NL03_2017_19
10 21 – 24 Agustus 2017 Monitoring LARAP Paket 05 dan 15 di Provinsi Sumatera Utara.OlehSocial Impact Specialist Tujuan monitoring adalah untuk berdiskusi dengan para pihak terkait LARAP terutama Paket 15 yang masih banyak Warga Terkena Dampak (WTP) yang belum dibayarkan. NL03_2017_20
11 21 – 25 Agustus 2017 Monitoring pelaksanaan RKPPL oleh Kontraktor pada Paket 13 dan 16 di Provinsi Bengkulu.OlehEnvironment Specialist Monitoring dilakukan pada paket –paket tersebut untuk memastikan syarat, perizinan dan aspek mengenai RKPPL telah terpenuhi. NL03_2017_21
12 23 – 26 Agustus 2017 Site Visit dan Monitoring Paket 05 dan 15 di Provinsi Sumatera Utara.Oleh :

  • Co – TL
  • QA Specialist
Monitoring dilakukan pada Paket 05 dan 15 untuk memastikan kelengkapan administrasi pelaksanaan proyek, serta mengadakan rapat hasil pemeriksaan lapangan di kantor proyek masing-masing paket 05 dan 15. NL03_2017_22
13 28 – 30 Agustus 2017 Kunjungan lapangan Road Safety Audit  Paket 15 (Sibolga – Bts. Tapsel) di Provinsi Sumatera Utara oleh:Road Safety Engineer Kunjungan dilakukan pada masa konstruksi untuk memastikan rambu dan fitur keselamatan jalan sesuai dengan ketentuan. NL03_2017_23
14 28 – 30 Agustus 2017 Monitoring pelaksanaan Paket 08 (Bts. Pariaman – Manggopoh) Provinsi  Sumatera BaratOleh:

  • Tim TPM dari Universitas Bung Hatta (UBH) Padang,

Didampingi oleh:

Community Development Officer CTC WINRIP.

Sebagai kewajiban TPM untuk melakukan monitoring pelaksanaan pekerjaan di lapangan terutama permasalahan yang berhubungan dengan masyarakat dan lingkungan sekitar proyek, ketaatan terhadap spesifikasi, dan manajemen hubungan antara stakeholder terkait. NL03_2017_24
15 4  September 2017 Pendampingan  Teknis Penjaminan Mutu (QA Training) WINRIP di Provinsi Sumatera Barat.Oleh :

  • Ketua Pelaksana Harian PMU
  • Civil Engineer Bank Dunia
  • Transport Consultant Bank Dunia
  • Co – Team Leader
  • Quality  Assurance Specialist
Pendampingan Teknis Penjaminan Mutu (QA Training) WINRIP diadakan bertujuan untuk :

  1. Meningkatkan kualitas pekerjaan konstruksi sipil dengan memberikan pelatihan penyegaran mengenai prinsip-prinsip pengendalian kualitas dan penjaminan mutu.
  2. Konsultasi dengan staf proyek WINRIP dan memberikan panduan mengenai kebutuhan peningkatan manajemen mutu yang lebih baik.

Pendampingan Teknis Penjaminan Mutu di Provinsi Sumatera Barat diikuti  oleh paket- paket: 21, 20, 14, 12, 08, dan 07, serta paket 16 dari Provinsi Bengkulu.

Peserta terdiri dari :

  • Unsur proyek yaitu PPK, Kaur TU
  • Unsur konsultan supervise yaitu: Tim DSC. Site Supervisor Engineer, Quality Engineer, Chief Inspector.

Unsur kontraktor yaitu:  General Superintendent dan Quality Control Manager.

NL03_2017_25
NL03_2017_26
16  5 – 8 September 2017 Pendampingan  Teknis Penjaminan Mutu on Site Training (di Base camp) untuk paket-paket di Provinsi Sumatera Barat.Oleh :

  • Ketua Pelaksana Harian PMU
  • Civil Engineer Bank Dunia
  • Transport Consultant Bank Dunia
  • Co – Team Leader
  • Quality  Assurance Specialist
 5 September 2017.Site Inspection dan Training di Base Camp Paket 21 dan 20. NL03_2017_27
NL03_2017_28
6 September 2017.
Site Inspection dan Training di Base Camp Paket 12 dan 14.
NL03_2017_29
NL03_2017_30
7 September 2017.
Site Inspection dan Training di Base Camp Paket 07.
NL03_2017_31
8 September 2017.
Quality inspection of Civil work dan Training di Base Camp di Paket 16.
NL03_2017_32
17  6 – 7 September 2017 Rapat evaluasi Rock Excavation (Blasting) Paket 05 di Provinsi Sumatera Utara.Oleh :Highway Engineer Rapat membahas pelaksanaan pengawasan Rock Excavation Paket 05 SP.Rampa-Poriaha. Rapat dilaksanakan di Kantor BBPJN II Medan, dipimpin oleh Ketua Tim Pengawas Rock Excavation (kasi Preservasi dan Peralatan Jalan BBPJN II) dan dihadiri oleh :

  • Tim Teknis Pengawasan, Kasi Teknik Rekonstruksi II, Ditjen Bina Marga,
  • PPK 12 (Sibolga CS)
  • Kontraktor pelaksana PT. Nusa Konstruksi
  • Konsultan Pengawas PT. Seecons (Site Supervision Engineer) DSC WINRIP
  • Highway Engineer CTC WINRIP
NL03_2017_33
18  6 – 9 September 2017 Rapat membahas Dokumen Evaluasi Lingkungan Hidup (DELH) dan cek basecamp management Paket 05 dan 15 di Provinsi Sumatera UtaraOleh :Environment Specialist Rapat koordinasi dengan para pihak terkait proyek melanjutkan rapat sebelumnya tentang pembahasan membahas  Dokumen Evaluasi Lingkungan Hidup (DELH).Dilanjutkan dengan Cek base camp management pada paket 05 dan 15 untuk memastikan bahwa kontraktor telah menerapkan prinsip base-camp dengan benar dan baik agar tidak terjadi pencemaran lingkungan di Base-camp. NL03_2017_34
19  10 – 11 September 2017 Pendampingan  Teknis Penjaminan Mutu (QA Training) WINRIP dilanjutkan dengan on Site Training pada Paket 05 dan 15 di Provinsi Sumatera Utara oleh :

  • Ketua Pelaksana Harian PMU
  • Civil Engineer Bank Dunia
  • Transport Consultant Bank Dunia
  • Co – Team Leader

–  Quality  Assurance Specialist

Pendampingan Teknis Penjaminan Mutu (QA Training) WINRIP diadakan bertujuan untuk:

  • Meningkatkan kualitas pekerjaan konstruksi sipil dengan memberikan pelatihan penyegaran mengenai prinsip-prinsip pengendalian kualitas dan penjaminan mutu.
  • Konsultasi dengan staf proyek WINRIP dan memberikan panduan mengenai kebutuhan peningkatan manajemen mutu yang lebih baik.

Pemeriksaan lokasi pekerjaan di lapangan serta diadakan in site training pada Paket 05 dan 15 tersebut.

Peserta Training terdiri dari :

  • Unsur proyek yaitu PPK, Kaur TU
  • Unsur konsultan supervise (DSC) yaitu Site Supervisor Engineer, Quality Engineer, Chief Inspector.
  • Unsur kontraktor yaitu: General Superintendent dan Quality Control Manager.
NL03_2017_35
NL03_2017_36
20 12 -14 September 2017 Pendampingan  Teknis Penjaminan Mutu (QA Training) WINRIP dilanjutkan dengan on Site Training pada Paket 13 di Provinsi Bengkulu dan 17 di Provinsi LampungOleh :

  • Ketua Pelaksana Harian PMU
  • Civil Engineer Bank Dunia
  • Transport Consultant Bank Dunia
  • Co – Team Leader

–  Quality  Assurance Specialist

Pendampingan Teknis Penjaminan Mutu (QA Training) WINRIP diadakan di Bengkulu bertujuan untuk:

  • Meningkatkan kualitas pekerjaan konstruksi sipil dengan memberikan pelatihan penyegaran mengenai prinsip-prinsip pengendalian kualitas dan penjaminan mutu.
  • Konsultasi dengan staf proyek WINRIP dan memberikan panduan mengenai kebutuhan peningkatan manajemen mutu yang lebih baik.

Peserta Training terdiri dari :

  • Unsur proyek yaitu PPK, Kaur TU
  • Unsur konsultan supervise (DSC) yaitu Site Supervisor Engineer, Quality Engineer, Chief Inspector.
  • Unsur kontraktor yaitu: General Superintendent dan Quality Control Manager.

13 September 2017.

Kunjungan lapangan ke Paket 13 di Base camp dan dilanjutkan training di base camp Paket 13 Sp. Rukis – Tj Kemuning.

14 September 2017.

Kunjungan lapangan ke Paket 17 di Base camp dan dilanjutkan training di base camp Paket 17 Sp. Gunung Kemala – Pg. Tampak.

NL03_2017_37
NL03_2017_38
NL03_2017_39
21  14 -16 September  2017 Monitoring TPM Paket 14 Painan Kambang – Provinsi Sumatera BaratOleh:

  • TPM dari Universitas Bung Hatta (UBH) Padang

Didampingi oleh:

Community Development Officer CTC WINRIP.

Sebagai kewajiban TPM  Paket 14 dari Universitas Bung Hatta untuk melakukan monitoring pelaksanaan pekerjaan di lapangan terutama permasalahan yang berhubungan dengan masyarakat dan lingkungan sekitar proyek, ketaatan terhadap spesifikasi, dan manajemen hubungan antara stakeholder terkait. NL03_2017_40
NL03_2017_41
22 16 – 18 September  2017 Misi World Bank mengenai Basecamp Management  and safeguard issue di Paket 13 dan 16 di  Provinsi Bengkulu oleh:

  • Ahli lingkungan Word Bank

Environmental specialist

Misi dilakukan untuk supervisi dan review safeguard dan progress base camp management di paket 13 dan 16, untuk  memastikan telah sesuai dengan ketentuan. NL03_2017_42
NL03_2017_43
23  18 – 20 September  2017 Monitoring LARAP pada Paket 07, 12 dan 14 di Provinsi Sumatera Barat oleh:
Social Impact Specialist
Tujuan monitoring adalah untuk berkoordinasi dengan PPK paket-paket terkait mengenai kemajuan pembebasan lahan, permasalahan dan solusinya sehingga dapat mempercepat pembebasahan lahan yang bermasalah pada paket 07, 12 dan 14. NL03_2017_44
24  26  September  2017 Rapat misi supervisi Bank Dunia terkait Pelaksanaan WINRIP Rapat dilaksanakan di Gedung Sapta Taruna lantai 5, dipimpin oleh Direktur Preservasi Jalan  selaku Ketua PIU WINRIP, dan dihadiri oleh :

  • Pejabat dan Staf BBPJN II Medan
  • Pejabat dan Staf BPJN III Padang
  • Kasudit KPSJ, Dit. PJJ selaku koordinator PMU
  • Staf Pemograman, Dit. PJJ
  • Staf Pemantauan dan Evaluasi, Dit PJJ
  • Staf Lingkungan dan Keselamatan Jalan, Dit. PJJ
  • Tim Word Bank
  • Tim DSC
  • Tim CTC
NL03_2017_45
NL03_2017_46
25 29  September  2017 Rapat misi supervisi Bank Dunia terkait Proyek WINRIP Rapat dilaksanakan di Gedung Baru, Ruang Rapat Utama Bapenas lantai 2, dan dihadiri oleh:

  1. Kementrian Pekerjaan Umum dan Perumahan Rakyat :
  • Direktur Preservasi Jalan, Ditjen Bina Marga
  • Direktur Pengembangan Jaringan Jalan, Ditjen Bina Marga
  • Direktur Pembangunan Jalan, Ditjen Bina Marga
  • Kepala Biro Perencanaan Anggaran dan Kerjasama Luar Negeri
  1. Kementrian Keuangan
  • Direktur Pinjaman dan Hibah; Ditjen Pengelolaan Pembiayaan dan Risiko (DJPPR)
  1. Kementrian PPN/Bappenas
  • Direktur Pendanaan Luar Negeri Multilateral, Deputi Bidang Pendanaan Pembangunan
  1. Lain-lain
  • Tim Misi World Bank
  • PMU WINRIP
  • CTC WINRIP
  • DSC WINRIP
NL03_2017_47
NL03_2017_48